Expansion of the storage and production hall for the production of toilet water
Scope of work:
- Preparation of executive design: construction, technology elements, electricity, automation and telecommunications, sanitary installations
- Designation of EX zones
- Preparation of a report on the environmental impact of the investment
- Participation in obtaining a final decision on the environmental conditions of consent to implement the project
- Participation in obtaining a final building permit decision
- Execution of construction works
- Carrying out works related to infrastructure and land development
- Construction of the following installations: sanitary, HVAC, electrical, lighting, telecommunications, process for the production of toilet water and automation
- Commissioning and testing of the installation, assistance and technical support, preparation of as-built documentation